Contractual ADC (Average Daily Cost)

The Contractual ADC (Average Daily Cost) means the cost of a resource when working on a project/delivery (or positioned on an opportunity).

 

Here is the detail of the formula in order to calculate it:

For an internal resource

Contrat ADC = Salary ADC + Contractual advantages ADC + Contractual expenses ADC

Salary ADC =[(monthly gross salary x charges) x 12] / number of annual working days

Contractual advantages ADC = Contractual advantages cost per day

Contractual expenses ADC = Contractual expenses cost per day

For an external resource 

Contrat ADC = excluding tax daily rate + (possible contractual advantages and contractual expenses ADC)

 